TSX- and ASX-listed Capstone Copper has advised of a delay in the planned restart of the Pinto Valley operation in Arizona owing to additional maintenance being required on a few of the major mechanical components of the primary crusher.
The company explains the Pinto Valley plant was expected to resume operations early in November, however, the company identified additional maintenance requirements during commissioning of the plant’s primary crusher, which extended the scope and duration of the planned maintenance – given that specific components need to be manufactured off-site by the original-equipment manufacturer.