Tanami Gold says blasting of the central and ventilation portals for the Groundrush Exploration Decline has been completed at the Central Tanami Project Joint Venture (CTPJV) in the Northern Territory of Australia, marking a significant milestone for the project.
Tanami and MGX Resources each hold a 50% interest in the CTPJV which is seeking to advance to a development decision in 2027.
Construction of the portals has been undertaken as part of the initial works under a A$38 million ($26 million) contract with Macmahon Underground Pty Ltd, a wholly owned subsidiary of Macmahon Holdings Limited, as announced at the end of August 2026.
The contract encompasses portal and ventilation establishment and the initial 3.5 km of decline development to a depth of circa 350 m over a period of 14 months. The decline will provide underground access for 33,000 m of infill resource definition drilling into the Groundrush gold deposit. The objective of the drilling is to convert over 400,000 oz of mineral resources currently classified as inferred into the higher confidence indicated category for mine design and development purposes. The infill drilling will commence in the latter stages of the decline construction period.
As previously reported, the CTPJV’s JORC 2012 resource totals 31 Mt at an average grade of 2.8 g/t Au for 2.8 Moz of contained gold, including 11 Mt at 3.3 g/t Au for 1.2 Moz of gold within the Groundrush gold deposit.
Tanami Executive Director, Brett Smith, said: “The establishment of the Groundrush Exploration Decline represents another key milestone in the CTPJV’s efforts in advancing the project working with our JV Partner, MGX.”
The post Macmahon blasts underground portals at Central Tanami Project Joint Venture appeared first on International Mining.