Italian steelmaker Pittini plans week-long stoppages at two plants as energy costs squeeze production

Italian long-steel producer Pittini Group is preparing to suspend steelmaking and rolling operations at its Siderpotenza and Acciaierie di Verona facilities from 30 November to 4 December 2026, according to industry reporting published on 17 November.

Energy costs drive restrictions

The planned interruptions reflect elevated electricity and gas costs that have disrupted electric-arc-furnace steel production across northern Italy. A further week of production restrictions in December is also under consideration.

Acciaierie di Verona operates an electric-arc furnace with approximately 1.1 million tonnes of annual capacity, while Siderpotenza has approximately 1 million tonnes of furnace capacity. Both sites manufacture long-steel products for construction and industrial markets.

Pressure spreads across the market

Other Italian producers have already adjusted operating schedules to avoid expensive electricity periods. The effects have spread into sales quotations and delivery planning, with manufacturers seeking higher prices to recover energy costs.

Industry participants reported drawing-quality wire rod prices approaching €740 per tonne, while producers were considering further increases following the withdrawal of some offers.

Shutdown plans remain unconfirmed

The reported Pittini shutdown schedule has not been independently confirmed through a company statement and should not be interpreted as a permanent closure decision.

The latest development adds a specific production timetable to the broader disruption already affecting Italian steelmaking. Continued electricity-price volatility risks reducing available supply and weakening the competitiveness of Europe’s scrap-based steel production.

The post Italian steelmaker Pittini plans week-long stoppages at two plants as energy costs squeeze production appeared first on Mining South East Europe.