Two operating presses advance Skouries toward commercial production

Eldorado Gold said the first two tailings filter presses at its Skouries mine in northern Greece are operational, allowing the plant to run continuously as throughput increases during commissioning. The milestone advances the project toward commercial production of sulphide ore.

Filter press commissioning

The tailings filtration facility has six Metso filter presses: five operating units and one installed spare. Four operating presses are required to support commercial production, while five are needed to reach nameplate throughput. The spare is intended to provide operational flexibility and allow maintenance without reducing throughput.

Commissioning of the remaining four presses was expected to be completed by year end, Eldorado Gold said. The company is progressively increasing throughput and optimizing plant performance as ramp-up continues.

Environmental design and production

President and CEO Christian Milau called the presses coming online “an important commissioning milestone.” He said filtered tailings are “a cornerstone of Skouries’ design” and a key component of the company’s Integrated Extractive Waste Management strategy, reflecting its commitment to mining technologies intended to enhance environmental performance, support operational reliability and maximize water recovery.

Over the life of the mine, Skouries is expected to produce an average of 140,000 oz of gold and 67 million lb of copper annually. The remaining press commissioning and the plant’s throughput ramp-up are the next steps toward commercial production.

The post Two operating presses advance Skouries toward commercial production appeared first on Europe Mining News.