Pasinex Resources restarted underground exploration drilling at Türkiye’s Pinargozu zinc mine on 7 October 2026, beginning an approximately 4,000-metre programme to test deeper zinc sulphide mineralisation and support longer-term mine development. The company described the programme on 10 November 2026.
The restart followed a pause of roughly two years and changes to the mine’s previous joint-venture arrangements. Drilling is planned from three stations on the +410 underground level; by 5 November, 207.5 metres had been completed at the first station.
Drilling and access plans
The plan allocates about 1,000 metres of drilling to the first station and 1,500 metres to each of the second and third. The work will test whether zinc sulphide zones extend deeper than historical workings and whether earlier intersections can be linked into a mineable geological model.
Underground access includes a planned 700-metre main drift, of which approximately 125 metres had been completed as of 7 November. The remaining access work is planned to continue into 2027. Pasinex is also using a second drilling unit at the +570 level to examine shorter-range extensions near existing workings.
Results remain preliminary
Prior exploration recorded high zinc readings in selected intervals. Some historical measurements, however, were obtained by portable X-ray fluorescence and are not substitutes for laboratory assays.
The campaign has not established additional compliant resources or reserves, and preliminary geological indications should not be treated as production forecasts. Pinargozu’s ability to sustain output will depend on converting drilling results into practical mine plans, completing underground access and managing mining and processing costs.
The work is a potential resource-replacement step, not a confirmed expansion in recoverable zinc supply.