Lucara Diamond raised its 2026 revenue forecast to US$140 million–US$160 million (€127 million–€145 million) on 13 November, after exceptional large-stone sales boosted third-quarter earnings at its Karowe mine in Botswana. The new range is above its previous guidance of US$100 million–US$130 million and may improve the company’s capacity to manage the mine’s investment programme.
Third-quarter revenue rose 19% to US$61.1 million (€55.3 million), Lucara reported. Sales included a 1,303-carat Type IIa diamond and other high-value stones.
Antwerp-based diamond trader HB Trading BV bought US$48.5 million (€43.9 million) of the quarter’s sales, roughly 79% of revenue. Antwerp is a major European diamond trading and distribution hub, making the Botswana mine a direct supplier to the hub despite its location in southern Africa.
Karowe processed 829,822 tonnes of ore and recovered approximately 96,767 carats during the quarter, including stones from historical tailings. Those production figures relate to existing operations, not the underground extension that is still being built.
Underground project moves into lateral development
The underground project progressed from shaft construction into lateral development during the third quarter. Contractors completed 466 metres of underground development.
As of 30 September, Lucara estimated that US$245.2 million (about €222 million) of project expenditure remained. Full-scale underground production is targeted for the first half of 2028 and has not yet started commercially.
Earlier bond listing and construction exposure
Lucara had previously issued US$350 million in senior secured bonds, which were admitted to trading on the Euronext ABM market in Oslo in September. The admission was an earlier event, not a new financing completed in November.
The company remains exposed to volatile prices for exceptional stones, sales concentration through a major Belgian counterparty, and the cost and scheduling risks of underground construction.