DPM Metals targets 850,000-tonne Vareš throughput by end-2026

DPM Metals processed approximately 143,100 tonnes of ore in the third quarter at its Vareš polymetallic operation in Bosnia and Herzegovina, and is targeting full design capacity by the end of 2026, the company said. The quarterly result forms part of reported progress in increasing production after Vareš had achieved commercial production.

DPM Metals says the operation is designed for annual throughput of approximately 850,000 tonnes. Vareš has not yet demonstrated full annualised design throughput; the latest figures reflect its quarterly operating performance and an updated ramp-up outlook, not a change in its production status.

The company expects to commission a second tailings filtration unit during November. It also expects Vareš to exceed the upper end of its earlier 2026 guidance for ore throughput and gold-equivalent production.

Legal issues remain under review

Vareš faces outstanding legal issues concerning the treatment of state-owned forest and forestry land under Bosnia and Herzegovina’s constitutional framework. The Constitutional Court issued a ruling concerning certain legal acts that requires the relevant authorities to review them.

The ruling did not terminate the concession agreement, and operations are continuing. Sustained processing performance and regulatory certainty are identified as the principal factors for assessing Vareš’s next development stage.