Abenójar Tungsten is advancing construction of its El Moto tungsten and gold mine in central Spain after raising approximately 170 million euros in a London stock-market flotation completed in October 2026. The company is targeting initial production in early 2029. Its proposed Deutsche Bank debt financing remains conditional.
Mine development
The underground decline had advanced 60 metres, and construction of a 100,000-cubic-metre water reservoir was complete. A pilot water-treatment plant was operating, while initial construction of waste-rock and tailings-disposal facilities was under way.
El Moto is designed to process 1.5 million tonnes of ore annually and produce approximately 422,656 metric tonne units of tungsten trioxide at steady state. The mine could become a new source of tungsten for European industrial supply chains.
Debt financing
Abenójar Tungsten has a financing term sheet with Deutsche Bank that has received conditional credit approval. No final facility agreement or disbursement has been announced, so the debt financing is not yet finalized.
A definitive facility agreement is expected in the first quarter of 2027, and financial close could follow in the second quarter of 2027. Physical construction progress reduces some uncertainty, but underground development, processing performance and execution of environmental controls remain important tests before El Moto can supply tungsten to industrial customers.