The government of Republika Srpska authorised a guarantee supporting approximately €25.6 million of borrowing by Elektroprivreda Republike Srpske for coal purchases required by the Ugljevik power plant, while separately advancing a proposed financing guarantee for the Gacko mining operation.
The Ugljevik financing is intended to fund the purchase of coal needed to maintain electricity generation and address fuel-supply constraints.
Further guarantee for Gacko
For the Gacko mine and power complex, the government accepted an initiative for a further guarantee covering approximately €4.6 million in prospective borrowing.
That financing would support capital works involving overburden removal, including excavation, loading, transport and waste-rock handling.
These activities are essential to maintaining access to coal reserves and improving continuity of lignite production.
Financing status: Government consent for the Ugljevik loan guarantee approved. The Gacko guarantee remains at initiative stage and requires completion of the credit-procurement procedure and a formal application. Neither approval should be treated as confirmation that loan funds have been received or spent.
The decisions highlight the continuing importance of mine-development expenditure and short-term financing for coal-dependent electricity systems in Southeast Europe, despite longer-term decarbonisation pressures.
The post Bosnia’s Republika Srpska approves coal-financing guarantees worth up to €30.2 million appeared first on Mining South East Europe.