Abenójar advances Spanish tungsten mine construction as debt financing remains conditional

Abenójar Tungsten is progressing construction of its El Moto tungsten and gold mine in central Spain after raising approximately €170 million through a London stock-market flotation completed in October.

Construction advances

In a 12 November 2026 update, the company reported that the underground decline had advanced 60 metres, construction of a 100,000-cubic-metre water reservoir had finished and a pilot water-treatment plant was operating. Initial construction of waste-rock and tailings-disposal facilities was also under way.

Production plans

The development is designed to process 1.5 million tonnes of ore annually and to produce approximately 422,656 metric tonne units of tungsten trioxide at steady state. Initial production is targeted for early 2029, making El Moto a potential new source of tungsten for European industrial supply chains.

Financing remains conditional

The company has a financing term sheet with Deutsche Bank that has received conditional credit approval. A definitive facility agreement is expected in the first quarter of 2027, followed by a possible financial close in the second quarter. The funding therefore remains conditional; no final facility or disbursement has been announced.

Remaining project tests

Physical progress reduces some construction uncertainty, but the debt package, underground development, processing performance and execution of environmental controls remain important tests before El Moto can deliver tungsten to industrial customers.