Hindustan Zinc announced on 16 November that its board had approved an approximately €7.7 billion investment programme designed to increase refined-metal production capacity from 1.1 million tonnes to 2 million tonnes annually.
Planned capacity expansion
The proposed programme covers the next three to five years and includes additional mining, smelting, silver refining and waste-processing capacity.
Major components include a new 500,000-tonne zinc smelter, a 200,000-tonne lead smelter and increased capacity at the Debari zinc complex.
Silver refining capacity is targeted to increase towards 1,500 tonnes annually.
The investment programme also provides for expanded ore production across the company’s existing mining portfolio and tailings reprocessing.
Funding the programme
Hindustan Zinc intends to finance the programme through internal cash generation and borrowings.
The company has established export activity involving European markets, giving the planned capacity expansion potential relevance to international zinc supply. However, no new dedicated European offtake agreement accompanied the announcement.
The approximately €7.7 billion headline figure includes certain projects and expenditures previously approved, meaning it should not be interpreted as entirely incremental capital.
European market impact
The board-approved spending is planned over several years; the full amount has not been borrowed, received or spent. No separate European financing commitment or binding European sales contract was announced.
The expansion could materially increase global refined zinc and lead supply, although the eventual effect on Europe will depend on export allocation and market competitiveness.
The post Hindustan Zinc approves €7.7 billion expansion to nearly double metal production capacity appeared first on Mining South East Europe.