Caledonia Mining announced on 12 November that operating problems at its Blanket gold mine in Zimbabwe had been resolved, following equipment commissioning and changes to its underground and processing operations.
Blanket operations restored
Two compressors commissioned on 31 October eliminated compressed-air shortages that had constrained access to higher-grade underground mining areas.
A new elution vessel commissioned in October helped recover more than half of approximately 1,100 ounces of gold previously retained within the processing system.
The refurbished Lima plant has increased throughput to approximately 160 tonnes per day, with a target of 200 tonnes per day.
Revenue and project plans
Caledonia reported third-quarter revenue equivalent to approximately €70.9 million, despite lower gold production.
The company is separately progressing its Bilboes gold project, where first production is targeted for the fourth quarter of 2028.
An interim bank financing agreement worth up to approximately €134.8 million was signed on 5 November, before the current reporting window. It provides a financing framework but should not be treated as newly received construction funds.
Financing remains in development
Equipment commissioning and processing recovery are confirmed. Bilboes’ interim lending agreement was previously signed; long-term project financing remains under development.
The immediate commercial benefit is the recovery of production efficiency at Blanket, while Bilboes remains the company’s larger capital-development undertaking.
The post Caledonia resolves Zimbabwe gold-processing bottlenecks and advances Bilboes preparations appeared first on Mining South East Europe.