Vulcan Energy Resources is mobilising a second company-owned drilling rig at its Lionheart lithium and geothermal project in Germany’s Upper Rhine Valley, as it works towards first production in the second half of 2028. Seven of the project’s 28 planned wells have been installed.
The V10 rig, rated at 2,000 horsepower, is being deployed to Trappelberg to support simultaneous drilling of production wells and reinjection wells. Vulcan has committed about €51 million to two heavy-duty rigs, operated through its Vercana drilling subsidiary. Owning the equipment gives Vulcan direct control over a central part of the development schedule amid competition for specialist rigs that can delay geothermal projects.
Planned output and remaining milestones
Lionheart is designed to produce around 24,000 tonnes of lithium annually, as well as estimated capacity of 275 GWh of renewable electricity and 560 GWh of heat. These are planned operating-capacity estimates, not volumes already being sold or delivered.
Vulcan says construction remains on schedule and within budget. The additional rig raises potential drilling throughput but does not establish that the remaining wells, processing systems or electricity and heat infrastructure are complete.
Commercial output still requires field development, plant construction, integrated commissioning and reliable operation at scale. Lionheart is a closely watched test of whether geothermal brines can provide a commercially viable European lithium source while supplying low-carbon power and heat. Greater drilling control may reduce contractor-related risk; key investment milestones include completed wells, operational processing facilities and sustained product output.
The post Vulcan deploys 2,000-horsepower rig at German lithium project appeared first on Europe Mining News.